Nine days of concentrated work rebuilt a critical rail junction—and trains south of Washington are running again.

Amtrak finished the First Street Tunnel work on time, replacing aging switches and track components before holiday travel.

Passengers boarding an Amtrak Vermonter train between two trains at Washington Union Station
Harrison Keely, CC BY 4.0

A nine-day outage south of Washington Union Station ended with trains moving again and a heavily used junction rebuilt beneath them. Amtrak completed its First Street Tunnel “Pause for Progress” on schedule and resumed operations October 26.

Crews replaced aging switches and crossovers at A-Interlocking, rehabilitated the tunnel track base and installed modern electric switch systems. The shutdown required coordination with Virginia Railway Express, Virginia’s passenger-rail authority, North Carolina’s transportation department, freight railroads and Metro.

The work does not modernize the entire Northeast Corridor, and riders absorbed temporary changes from October 16 through 26. Its value is concrete: a planned disruption ended when promised, with old components replaced before the holiday rush.

Source: Amtrak ·

Sources & notes

Nine-day construction project completed October 26; broader corridor needs remain.